SilverCrest Successfully Completes New Mill Commissioning at Santa Elena Mine

SilverCrest Mines Inc. is pleased to announce that the new 3,000 tonne- per-day mill and facilities (CCD-Merrill Crowe recovery) at its 100% owned Santa Elena Mine has been successfully commissioned.

The commissioning period began in early May, 2014, and planned for 3 months of ramp-up, which was completed as of August 1, 2014. The Santa Elena Mine is currently transitioning from an open pit heap leach operation to a conventional 3,000 tpd conventional mill facility and underground operation.

N. Eric Fier, President and COO stated; "The announcement of commissioning completion for the new Santa Elena mill and facilities is another major milestone achieved as SilverCrest continues systematic and responsible growth. Our dedicated construction, commissioning and operating teams should be congratulated on their continued efforts toward achieving targets under strict schedules and cash control protocols. We will continue to adjust and optimize all the components of the facilities in efforts to achieve through-put tonnages at or above the nameplate capacity of 3,000 tpd. Our near term focus now turns to achieving further milestones, including underground stope production in August and free cash flow in Q3, 2014."

In determining commissioning completion, management considered the following criteria;

  • Achieving greater than 80% of nameplate capacity (3,000 tpd) over a reasonable period of continuous production.
  • Achieving average startup recovery rates of 82% gold and 65% silver. Average mine life recovery rates are projected at 92% gold and 67.5% silver.
  • Dore production from the new mill exceeding budget estimates.
  • All major components of the mill and facilities completed and operating to the satisfaction of management and independent commissioning team.
  • Completion of budgeted capital expenditures.
  • Achieving positive operating cash flows from expanded operations including mill.

For 30 continuous days through to early August, 2014, the mill through-put ranged from 1,485 to 3,144 tpd and achieved an average of 2,524 tpd or 84% of the 3,000 tpd nameplate capacity. In July, 1,516 ounces of gold and 81,818 ounces of silver (excluding residual leached ounces from pad production) were produced and which exceeded budgeted production of 1,255 ounces of gold and 74,325 ounces of silver. Startup recoveries of gold and silver in July were 82% and 65%, respectively, compared to budgeted start up recoveries of 83% and 62%. All of the above commissioning criteria have been met to the satisfaction of management.

As planned, the mill feed during the commissioning period came from the leach pad reserve (pad ore). Blending of higher grade underground ore is expected to commence during Q3, 2014. Approximately, 69,000 tonnes of pad ore that was milled in July graded 0.84 gpt Au and 56.80 gpt Ag, which are approximately 33% higher for gold and 58% higher for silver than budgeted grades of 0.63 gpt Au and 36.0 gpt Ag.

Underground stope production is the next milestone in the transition plan at Santa Elena. Production from the first underground stope is planned for August. This initial stope will be mined using standard long hole stoping methods. As of July 31, approximately 32,225 tonnes of underground development ore have been stockpiled for mill processing in Q3, 2014. The average stockpile grade is 1.63 gpt Au and 118.91 gpt Ag, which is consistent with current reserve models.

Source: http://www.silvercrestmines.com/

Tell Us What You Think

Do you have a review, update or anything you would like to add to this news story?

Leave your feedback
Your comment type
Submit

While we only use edited and approved content for Azthena answers, it may on occasions provide incorrect responses. Please confirm any data provided with the related suppliers or authors. We do not provide medical advice, if you search for medical information you must always consult a medical professional before acting on any information provided.

Your questions, but not your email details will be shared with OpenAI and retained for 30 days in accordance with their privacy principles.

Please do not ask questions that use sensitive or confidential information.

Read the full Terms & Conditions.