Posted in | News | Gold

Orezone Provides Update on Feasibility Study at Bomboré Gold Project

Orezone Gold Corporation The Company is pleased to provide the following update on the feasibility study work at its 100%-owned Bomboré Gold Project in Burkina Faso.

"The technical work is progressing well and we are pleased with the continued positive results that reinforce our preliminary testwork, guidance and designs," said Tim Miller, Chief Operating Officer for Orezone. "We are on schedule to complete the study in Q1 2015 and apply for a mining permit to develop the project in Q2 2015."

Metallurgical Testing

Kappes Cassiday & Associates (KCA) in Reno, Nevada has provided the company with highlights from the ongoing scrubbing and leaching tests performed on 2.2 tonnes of representative oxide and semi oxidized material. The material was divided into nine batches that would represent both the individual rock types and composites of what would be representative run of mine (ROM) material. Final results from the first three of the nine test batches have been received and are reflected in this release. The testwork is based on a flow sheet that combines scrubbing and screening of ROM material before a split circuit of heap leaching and agitated leach tanks (CIL). Each circuit will process approximately half of the total ROM material; the finer material (-0.212 mm) is delivered to the leach tanks and the remaining coarser material to the heap leach.

Test results to date continue to indicate that the overall gold recovery from the combined heap leach and CIL circuits will be between 80% and 90% on oxide materials. The saprolitic layer (fully oxidized material) exhibits the highest recoveries, with over 20% of the gold recovered in the short scrubbing process. The overall saprolite recoveries vary from up to 90% with head grades near 1.0 g/t to 80% for material just under 0.6 g Au/t. Preliminary assay results indicate that the tails are fairly constant at 0.08 to 0.1 g/t. The lower transition material (bottom half of the semi-oxidized material near the fresh rock contact) tested to date with a head grade of 0.6 g/t exhibits scrubber recoveries of 10% and an overall recovery of 67%. Although higher grade transition batches are not yet complete, the preliminary tail assays appear to be similarly consistent to that of the saprolite batches indicating that recoveries for the transition material may also be dependent on the head grade.

Rheological and solid liquid separation testing is also complete on the -0.212 mm fraction (pre and post leach) and results are consistent with previous tests that have been used to date in the design work for the feasibility study. The plant flow sheet is based on a ROM stockpile providing blended feed to a mineral sizer at a rate of 15,000 tpd (5.5 Mt/yr). Mineral sizer product reports to a stockpile that feeds a 5.2 m x 10.0 m rotary scrubber. Scrubber product passes over a vibrating double deck screen that sends the + 9.5 mm fraction to the heap leach feed stockpile, and the - 9.5 mm fraction to a cyclones and screw classifiers with the scrubber solution. The cyclones and screw classifiers remove the +0.212 mm material, which is sent to the heap leach feed stockpile, and the -0.212 mm material is then thickened to 48% solids in a 41m diameter thickener and pumped to the CIL circuit, consisting of a series of five 15 m diameter CIL tanks. CIL tails report to the nested tails facility which is integral to the heap leach pad, and loaded carbon is processed in a standard carbon strip circuit to recover the gold.

The heap leach material is transported via conveyor to a stacking system on the leach pad, where material is retreat-stacked in 8 m lifts. Compacted permeability testwork has demonstrated adequate permeability to a stacking height of 64 m without the need for cement agglomeration or interlift liners. Standard drip emitters are used to leach the stacked material, with pregnant solution reporting back to the scrubber circuit, eliminating the need for a separate carbon in column (CIC) processing circuit for the heap leach pregnant solution.

Mine Plan and Pit Optimization Studies

The Company is working with RPA Inc. ("RPA") to update open pit optimizations and develop a new mine plan (based on the April 2013 resource model) for the feasibility study. RPA has completed the optimization of the resources and has begun work on the pit design. Work on the mine plan will commence immediately and should be completed early in Q1 2015.

Geotechnical Studies

Golder and Associates based in Reno, Nevada are carrying out the geotechnical work required for the design of the nested tails/heap leach facility, process facility and waste rock storage. A small confirmatory field program will be completed in the coming weeks, with final design of the facilities available by Q1 2015.

All work on the feasibility study is on schedule to be completed by year end 2014, with report writing and compilation of the final document to be completed in Q1 2015. Work on the environmental and social impact assessment and relocation plan will continue into Q2 2015 in order to apply for a mining permit. A resource update is also expected in Q1 2015.

About Orezone Gold Corporation

Orezone is a Canadian company with a gold discovery track record of +12 Moz and recent mine development experience in Burkina Faso, West Africa. The Company owns a 100% interest in Bomboré, the largest undeveloped oxide gold deposit in West Africa which is situated 85 km east of the capital city, adjacent to an international highway. The Company is continuing with various technical studies in order to be in a position to complete a full feasibility study and an application for a mining permit in H1 2015.

Carl Defilippi of Kappes Cassiday & Associates; Glen Ehasoo of RPA Inc.; Tim Miller, COO and Ron Little, CEO of Orezone, are Qualified Persons under National Instrument 43-101 and have reviewed the information in this release.

Source: http://www.orezone.com/

Citations

Please use one of the following formats to cite this article in your essay, paper or report:

  • APA

    Orezone Gold Corporation. (2019, February 17). Orezone Provides Update on Feasibility Study at Bomboré Gold Project. AZoMining. Retrieved on April 20, 2024 from https://www.azomining.com/News.aspx?newsID=10750.

  • MLA

    Orezone Gold Corporation. "Orezone Provides Update on Feasibility Study at Bomboré Gold Project". AZoMining. 20 April 2024. <https://www.azomining.com/News.aspx?newsID=10750>.

  • Chicago

    Orezone Gold Corporation. "Orezone Provides Update on Feasibility Study at Bomboré Gold Project". AZoMining. https://www.azomining.com/News.aspx?newsID=10750. (accessed April 20, 2024).

  • Harvard

    Orezone Gold Corporation. 2019. Orezone Provides Update on Feasibility Study at Bomboré Gold Project. AZoMining, viewed 20 April 2024, https://www.azomining.com/News.aspx?newsID=10750.

Tell Us What You Think

Do you have a review, update or anything you would like to add to this news story?

Leave your feedback
Your comment type
Submit

While we only use edited and approved content for Azthena answers, it may on occasions provide incorrect responses. Please confirm any data provided with the related suppliers or authors. We do not provide medical advice, if you search for medical information you must always consult a medical professional before acting on any information provided.

Your questions, but not your email details will be shared with OpenAI and retained for 30 days in accordance with their privacy principles.

Please do not ask questions that use sensitive or confidential information.

Read the full Terms & Conditions.