Posted in | Gold | Mining Business

Crescent Gold Provides Details on Mining Operations at Laverton

Crescent Gold Limited (TSX:CRA)(ASX:CRE)(FRANKFURT:CRE5) -As announced on February 17th, the mining operations at Laverton were temporarily suspended as a result of severe weather conditions that caused extensive flooding regionally.

A review of the impact on the operations at Laverton is ongoing. The Company was able to evacuate all staff and contractors safely from the flooded camp, and water levels receded to enable some staff to move back into camp shortly afterwards.

Mining operations have recommenced at Craiggiemore and Grouse pits and the Mary Mac South pit has been completely dewatered with preparations for mining operations to commence shortly.

Haulage roads from Laverton pits to Barrick Granny Smith sustained minor damage and require the roads to dry before being able to recommence haulage. Further rains have hampered haulage but assuming no additional rains in the region, haulage is anticipated to recommence in the next few days. The haul road to the higher grade Fish open pit sustained more significant damage that continues to be assessed. The decision has been made to demobilise the digger from Fish until the haul road is repaired.

The impact of the rains on the operations due to inability to haul to Barrick Granny Smith has led to a reduction in our processing at Barrick by 18 days. This has had a negative impact on production during the quarter. Final reconciliations from Barrick are not yet available, but it is anticipated that production, which was budgeted to be approximately 27,000 ounces will be in the order of 15,000 ounces. The combination of the rains in the December quarter, leading to reduced production and the current quarters production issues detailed above, have led to a reduction in expected revenue. The reduction in revenue combined with additional costs associated with the flooding has required the Company to draw on funds recently raised, which has altered the use of proceeds.

The Company is in the process of revising production scheduling and budgets for the next twelve months and reviewing its insurance position and a further announcement will be made when details are finalised.

Source: Crescent Gold Limited

Citations

Please use one of the following formats to cite this article in your essay, paper or report:

  • APA

    Crescent Gold Limited. (2019, February 18). Crescent Gold Provides Details on Mining Operations at Laverton. AZoMining. Retrieved on May 20, 2019 from https://www.azomining.com/News.aspx?newsID=3587.

  • MLA

    Crescent Gold Limited. "Crescent Gold Provides Details on Mining Operations at Laverton". AZoMining. 20 May 2019. <https://www.azomining.com/News.aspx?newsID=3587>.

  • Chicago

    Crescent Gold Limited. "Crescent Gold Provides Details on Mining Operations at Laverton". AZoMining. https://www.azomining.com/News.aspx?newsID=3587. (accessed May 20, 2019).

  • Harvard

    Crescent Gold Limited. 2019. Crescent Gold Provides Details on Mining Operations at Laverton. AZoMining, viewed 20 May 2019, https://www.azomining.com/News.aspx?newsID=3587.

Tell Us What You Think

Do you have a review, update or anything you would like to add to this news story?

Leave your feedback
Submit