Peregrine Provides Update on Chidliak Diamond Project

Peregrine Diamonds Ltd. ("Peregrine" or "the Company") is pleased to provide an update on its 100 percent-owned Chidliak diamond project ("Chidliak" or the "Project"). Chidliak is located 120 kilometres northeast of Iqaluit, the capital of Nunavut, Canada.

The Company's objective is to advance the Project to diamond production in phases, with the first phase of development centered on CH-6, CH-7 and CH-44 ("the Phase One Kimberlites"), three of at least eight kimberlite pipes at Chidliak known to have economic potential. Commencing in 2016, Peregrine plans to confirm additional diamond resources in other kimberlites with economic potential. To date 71 kimberlites have been discovered at Chidliak, 42 of which are diamondiferous. Diamond testing has been deferred on 24 kimberlites. Peregrine is optimistic that more kimberlite pipes will be discovered at Chidliak in the future.

The work programs completed in 2014 and planned for 2015 are designed to confirm diamond resources in the Phase One Kimberlites. Once confirmed, these resources would form the foundation of an independent, NI 43-101-compliant, Preliminary Economic Assessment ("PEA") to be completed in 2016.

Resource development work completed in 2014 includes the acquisition and delivery to Iqaluit of drilling and support equipment required for the 2015 bulk sampling program and resource definition drilling of the Phase One Kimberlites. Exploration work completed in 2014 includes initial core drilling on the CH-46 kimberlite as a follow-up to encouraging microdiamond results and the discovery of two new kimberlites.

2015 RESOURCE DEVELOPMENT PROGRAM

Bulk samples from the Phase One Kimberlites will be obtained by large diameter RC drilling (up to 26 inch/66 cm diameter) in 2015. The work is designed to confirm continuity of diamond grade throughout the kimberlite bodies and obtain additional parcels of diamonds for valuation. If results warrant, Peregrine would prepare maiden resource statements for CH-7 and CH-44 and update the existing CH-6 resource.

In preparation for the 2015 program a total of 421 tonnes of material, including the large diameter RC drill and all required support equipment and supplies, was successfully mobilised to Iqaluit on the 2014 sealift. Mobilisation of the equipment into the Chidliak site from Iqaluit is scheduled to commence in January, 2015 via an overland winter trail and Hercules transport aircraft. Camp build-outs and related fuel staging in support of the bulk sample program were completed this summer. All of the permits required to conduct the 2015 bulk sample program have been received.

Preparation of the winter trail and staging area in Iqaluit will begin this month. A crew has mobilised to Chidliak and has begun site preparations, including construction of the ice strip for the Hercules.

SUMMER 2014 CHIDLIAK PROGRAM UPDATE

Details of the 2014 program were reported on September 2, 2014. Additional 2014 activities include:

  • Core and RC drilling at CH-6, CH-7 and CH-44
    Logging and sampling of the 3,305 metres of drill core from the Phase One Kimberlites is now complete. Approximately 1,418 kilograms of kimberlite were submitted to the Saskatchewan Research Council ("the SRC") for microdiamond testing. A small diameter RC drill completed an additional 71 metres in five holes to constrain overburden depth and establish near-surface contacts at CH-06. The drill and diamond results are being integrated into the existing geologic models of the Phase One Kimberlites. Revised tonnage estimates for CH-7 and CH-44 and a new estimate of the CH-6 resource, are expected in January 2015.
  • Core drilling outlines CH-46
    Initial microdiamond results from CH-46 are consistent with economic potential. Three core holes totalling 392 metres intersected 134 metres of kimberlite at CH-46, defining a north-south trending pipe with surface dimensions of 75 by 30 metres. The pipe remains open to the north and south. Core logging suggests CH-46 is comprised of volcaniclastic kimberlite with moderately abundant olivine macrocrysts and indicator minerals, and limestone and basement xenoliths. A representative 225 kilogram microdiamond sample has been submitted to the SRC for analysis. As reported on June 26, 2014, 246 diamonds greater than the 0.106 mm sieve were recovered from 80 kg of 2010-era CH-46 RC drill chips.
  • New kimberlite discoveries
    Six geophysical targets were tested by RC drilling this summer resulting in the discovery of two new kimberlites, CH-69 and CH-70, that could represent dyke-like structures. In addition, a previously unnamed kimberlite dyke discovered in 2010 was designated CH-71.
    • CH-69. Approximately 1.8 metres of kimberlite was intersected in an inclined RC hole targeting a segmented linear magnetic feature located 3.7 km northeast of Discovery camp.
    • CH-70. Approximately 0.9 metres of kimberlite was intersected in an inclined RC hole targeting a residual ground gravity low anomaly that coincides with a circular magnetic anomaly at the north end of the "String of Pearls", approximately 600 metres north of the CH-6 kimberlite.
    • CH-71. Approximately 5.2 metres of kimberlite was intersected by RC drilling in 2010 in an inclined hole targeting a linear magnetic feature located 15.6 km northeast of Discovery camp.
  • Prospecting and till sampling
    The areas around six known kimberlites and 20 geophysical anomalies were evaluated by prospecting and mapping, resulting in the discovery of the CH-68 kimberlite which was reported on September 2, 2014. In addition, 146 till samples were collected to better define unexplained kimberlite indicator mineral anomalies and 75 line kilometres of infill and high-resolution ground magnetic surveying was completed.

Results from the 2014 exploration program together with the extensive Chidliak exploration database are being evaluated to prioritize kimberlite targets for evaluation in 2015.

Dr. Herman Grütter, Professional Geologist and Peregrine's Program Manager, Chidliak Exploration, is a Qualified Person and is responsible for the design and conduct of the exploration programs at Chidliak. Mr. Alan O'Connor, Peregrine's Program Manager, Chidliak Resource Evaluation, is a Qualified Person and is responsible for the design and conduct of bulk sampling programs at Chidliak. Messrs. Grütter and O'Connor have reviewed this release and approve of its contents.

Source: http://www.pdiam.com/

Tell Us What You Think

Do you have a review, update or anything you would like to add to this news story?

Leave your feedback
Your comment type
Submit

While we only use edited and approved content for Azthena answers, it may on occasions provide incorrect responses. Please confirm any data provided with the related suppliers or authors. We do not provide medical advice, if you search for medical information you must always consult a medical professional before acting on any information provided.

Your questions, but not your email details will be shared with OpenAI and retained for 30 days in accordance with their privacy principles.

Please do not ask questions that use sensitive or confidential information.

Read the full Terms & Conditions.