Posted in | News | Copper | Mining Business

First Quantum Minerals Provides Update on Key Developments

First Quantum Minerals Ltd. today provided an update on key developments and actions in response to the low commodity prices and market volatility.

In outlining the actions completed or underway, Philip Pascall, Chairman and CEO, said "We have taken clear and decisive actions to protect First Quantum in the current market conditions. Our focus has been clear. It is first to ensure that profitability and cash flow from our mining operations are maximized and protected in these volatile market conditions and sustained lower commodity prices and second, that cash outflows are limited to essential and economically attractive projects so that our balance sheet integrity is maintained.

"Additional initiatives to further strengthen the balance sheet are being prioritized and are under active review. We will report further on these as appropriate."

KEY DEVELOPMENTS AND INITIATIVES:

Terms of a replacement Cobre Panama precious metals stream agreement finalized; capital costs estimate lowered

  • A revised precious metal stream agreement has been agreed with Franco-Nevada Corporation ("Franco-Nevada"). Under the revised agreement, it is expected that Franco-Nevada's initial contribution of between $330 million to $340 million will be paid to First Quantum during October. Additional details are contained in a separate joint news release.
  • The estimated capital cost of the Company's flagship project, Cobre Panama, has been reviewed in detail and reappraised. It is now estimated the total project cost will be $5.95 billion, approximately 7% below previous estimates with potential for further improvements.
  • Capital costs have been reduced due to better construction efficiency, continued optimization of detailed design and lower costs for equipment and bulk materials such as rebar and structural steel.
  • Overall the project is approximately 35% complete and experience to date allows greater confidence in forecasting total project costs. The project remains on track for process commissioning and first concentrate production in late 2017.
  • The port is now a fully operational and has received direct international shipments.
  • Early priority is being given to the completion of the power station taking advantage of virtually all required materials being available on-site. Mechanical installation works are progressing well.
  • Project costs incurred to date amount to $2.621 billion of which First Quantum's partner in the project, KPMC, has contributed $524 million. The remaining estimated costs to completion will be met by an additional contribution from KPMC of $666 million, $1 billion payable by Franco-Nevada under the precious metal streaming agreement and $1.663 billion by First Quantum.

Zambian power stabilizing; Sentinel anticipates commercial-level production by end of 2015

  • The Zambian power situation is stabilizing. Full power of 153MW is currently being provided to the Kansanshi mine and smelter and 55MW to the one power line currently connected to the Sentinel mine.
  • Sentinel's ramp-up to date has been affected by the limited power supply. Despite this, good progress has been made. Construction of the second power line connecting Sentinel to Lusaka West is complete and scheduled to be energized shortly. Once the second power line is connected and energized, Sentinel will be entitled to its full power requirement of 160MW. This will allow for the mine to ramp-up towards commercial-level production expected by the end of 2015.
  • ZESCO, the state-run power company, has requested the mining industry to use supplementary power for 30% of their requirements. Discussions are currently underway regarding the related tariffs for this supplementary power. The Company expects full production at both Kansanshi and Sentinel through the purchase and sharing of this power.
  • It is expected that the country's generating capacity will improve following the rainy season starting in November. In addition, approximately 400MW of new power generation capacity is expected online in Zambia in 2016 from projects nearing completion (300MW thermal and 100MW hydro).

Production and cost guidance for 2015 revised

  • Copper production for 2015 is now expected to be between 385,000 and 410,000 tonnes excluding Sentinel pre-commercial commissioning production of between 30,000 and 50,000 tonnes.
  • The C1 cost estimate is lowered to between $1.20 and $1.35 per pound.

Citations

Please use one of the following formats to cite this article in your essay, paper or report:

  • APA

    First Quantum Minerals Ltd.. (2019, February 17). First Quantum Minerals Provides Update on Key Developments. AZoMining. Retrieved on November 08, 2024 from https://www.azomining.com/News.aspx?newsID=12118.

  • MLA

    First Quantum Minerals Ltd.. "First Quantum Minerals Provides Update on Key Developments". AZoMining. 08 November 2024. <https://www.azomining.com/News.aspx?newsID=12118>.

  • Chicago

    First Quantum Minerals Ltd.. "First Quantum Minerals Provides Update on Key Developments". AZoMining. https://www.azomining.com/News.aspx?newsID=12118. (accessed November 08, 2024).

  • Harvard

    First Quantum Minerals Ltd.. 2019. First Quantum Minerals Provides Update on Key Developments. AZoMining, viewed 08 November 2024, https://www.azomining.com/News.aspx?newsID=12118.

Tell Us What You Think

Do you have a review, update or anything you would like to add to this news story?

Leave your feedback
Your comment type
Submit

While we only use edited and approved content for Azthena answers, it may on occasions provide incorrect responses. Please confirm any data provided with the related suppliers or authors. We do not provide medical advice, if you search for medical information you must always consult a medical professional before acting on any information provided.

Your questions, but not your email details will be shared with OpenAI and retained for 30 days in accordance with their privacy principles.

Please do not ask questions that use sensitive or confidential information.

Read the full Terms & Conditions.