Posted in | News | Gold | Mining Business

Torex Reports First Gold Pour from El Limon-Guajes Mine

Torex Gold Resources Inc. announced today its first gold pour of an estimated 350 ounces, and a similar amount of silver, in Dore, from its 100% owned El Limon-Guajes Mine (ELG) in southwest Mexico.

The entire processing circuit, from crushing through to dry stack tailings disposal, is now operational and has been used in the production of these first ounces.

Fred Stanford, President & CEO of Torex stated: "This is an exciting milestone and we want to thank the thousands of construction, mining, processing, support, and service personnel, and their leaders, that have efficiently and effectively turned intentions into reality. For the uninitiated, it can be difficult to envision the number and size of the hurdles that they must clear in order to build a mine, plant, and infrastructure of this scale and complexity. Their accomplishments tend to be 'unsung' and we would like to take this moment to acknowledge their impressive achievement in getting this project built on time and on budget."

Commercial Production Is Expected To Be Achieved On Schedule In Q2/16

Mining from the Guajes pit is ahead of schedule and the mine plan has been adjusted to allow for the drawdown of the ore stockpile through 2016. In the processing plant, the ramp-up has started with the utilization of 6 of 11 leach tanks and 5 of 7 of the tailings filters. As production volumes increase, additional leach and filtration capacity will be utilized. Construction of the remaining tanks and filters are completed and commissioning is underway.

Full Production Is Expected To Be Achieved Ahead Of The Original Schedule Of Q1/17

Ore from the El Limon pit is necessary to achieve full production and with the successful resettlement of the La Fundicion village, the focus has shifted to road building and pre-stripping on the El Limon ridge. Both of these activities are progressing smoothly. Construction of the El Limon crusher continues to advance ahead of schedule and assembly of the RopeCon is effectively complete and will be commissioned after the completion of the El Limon crusher, which provides the feed to the RopeCon. The commissioning of both the crusher and RopeCon is anticipated for Q2/16.

Future Updates And Guidance

Construction continues on non-process related infrastructure, i.e. the truck maintenance shop, the second village, some rainy season water control structures, etc. Updates on continuing ancillary construction progress will be provided as specific construction activities conclude.

Due to the many unknowns during the start-up of a new processing plant, it is challenging for the Company to provide estimates of quarterly production through the ramp up period. Therefore, Torex will provide quarterly updates on the production ramp up progress that has been accomplished and will refrain from forward looking quarterly guidance during 2016.

Source: http://www.torexgold.com/

Tell Us What You Think

Do you have a review, update or anything you would like to add to this news story?

Leave your feedback
Your comment type
Submit

While we only use edited and approved content for Azthena answers, it may on occasions provide incorrect responses. Please confirm any data provided with the related suppliers or authors. We do not provide medical advice, if you search for medical information you must always consult a medical professional before acting on any information provided.

Your questions, but not your email details will be shared with OpenAI and retained for 30 days in accordance with their privacy principles.

Please do not ask questions that use sensitive or confidential information.

Read the full Terms & Conditions.