Mine development is well advanced at the Vertikalny Central deposit, with construction now approximately 60% complete. Project expenditure to date is approximately US$30 million of the proposed US$49.9 million budget with the project expected to come in under the Feasibility Study budget. Due to an unusually early winter the summer overland supply route has been curtailed until the winter road is fully frozen, which has resulting in a short delay in starting production ramp- up from early in Q1 2017 to the end of Q1 2017.
In addition to the mine development at Mangazeisky silver project, the Company has also successfully expanded its mineral resource base in all categories. These improvements have resulted in the Company updating its feasibility study for the Vertikalny deposit in October resulting in significant benefits and in the initiation of a Preliminary Economic Assessment ("PEA") at its Mangazeisky North deposit, which assessment is scheduled for completion early in Q1 2017."
The following important construction and development milestones were completed in 2016 to date:
- Remaining materials and equipment required for construction and commissioning are either now on site, or being prepared for transport from Yakutsk to site.
- Mangazeisky mine camp is near completion, including the engineers' quarters and crew dormitory, technical and medical offices, Wi-Fi and communications centre and cafeteria.
- The diesel power station has been installed and in the process of being connected to fuel supply and power cables with commissioning works planned for late November.
- Foundations and installation of fuel tanks and boiler system; installed the first phase of the main process building and adjacent garage heating system and completed the pre-commissioning testing of the heating system. The system is now in operation.
- Tailings storage facility design updates are being reviewed and detailed final design being completed to allow construction work to commence.
- Water supply borehole No. 2 is being drilled, water continues to be pumped from borehole No. 1. Water testing is ongoing for quality and further testing of water volumes will be done when borehole No. 2 is completed.
- Construction and weather sheeting of the main processing plant has been completed; the foundation and installation of ball mill within the plant has been completed and the mechanical assembly is close to completion.
- Completed the cyanidation tanks foundation and installed tanks, now working on completing the piping installation across the processing facility as well as continuing with the installation of electrical cabling.
- The workshop, warehouse and reagents storage facilities are near completion and are being fitted for heating and electrical systems.
Filing of Updated Feasibility Study Technical Report
The Company is also pleased to announce that on November 17, 2016 it filed the NI 43-101 technical report ("Technical Report") for the Updated Feasibility Study on the Mangazeisky silver project, Republic of Sakha (Yakutia), Russian Federation. The Technical Report supports the Company's announcement of October 4, 2016. To view and download the Technical Report, please visit www.sedar.com under the Company's profile. The Technical Report will also be available on the Company's website at www.silverbearresources.com.
Amendment to the October 4, 2016 Press Release
Due to a typographical error, the Company would also want to apologize to Mr. Michael Beare of SRK Consulting (UK) whose name was inadvertently listed under the Qualified Persons list for the Updated Feasibility Study. Mr. Beare was one of the Qualified Person responsible for the NI 43-101June 2016 Feasibility Study. Below is the revised Qualified Person's list for the October 4, 2016 press release.
Tetra Tech
Anton von Wielligh, BSC (Hons), PrEng, SAIMM
Arunasalam Vathavooran, PhD, CEng, MIMMM
Damian Hicks, MIEAust CPEng
Guy Roemer, PE
Jacques du Toit, CEng, PrEng, MScEng, PMP
Laszlo Bodi, MSc, CEng, PEng
Rene Gharapetian, PEng
Robert Davies, BSc (Hons), CGeol, EurGeol, FGS
Sabry Abdel Hafez, PhD, PEng
Saunjay Duggal, MSc, Peng
SRK (UK)
Houcyne El Idrysy, PhD, CGeol, FGS
Krysztof Czajewski, BSc, PEng
Max Brown, BSc, MSc, CEng, MIMMM
ERM
Derek Chubb, PEng