Posted in | News | Gold

Rio Alto Mining Updates on La Arena Gold Oxide Project in Peru

Rio Alto Mining Limited (TSX VENTURE:RIO)(OTCQX:RIOAF)(BVLAC:RIO)(DBFrankfurt:MS2) has provided an update on activities at the La Arena Gold Oxide Project located in Peru.

Construction activities began at La Arena in August 2010, immediately following the approval of the Gold Oxide Project Environmental Impact Study and substantial progress has been made during the past five months.

A civil construction contract was awarded to civil contractor GyM - Stracon´s, Consorcio Tiwu in August.

To date,

  • 100 percent of the earthworks related to the construction of the nine hectare run of mine (ROM) Pad 1A have been completed and 70 percent of the pad has been lined with geomembrane.
  • 100 percent of the earthworks related to the 60,000 m3 PLS (Pregnant Liquor Storage) Pond has been completed and sub-drainage installation has commenced. Once the sub-drainage system has been completed lining of the PLS pond will be completed.
  • 100 percent of the civil work related to the plant site for the adsorption / desorption gold processing plant has been completed.
  • Construction of a 300 man camp accommodation, mess facilities and mine offices has commenced with the mine offices due for completion by the end of December, the mess facilities are due for completion at end of January and the camp accommodation facilities are due for completion at the end of March.
  • Pad overliner material production is underway and will be completed for ore loading in January.
  • Construction of a new school for 300 students, ranging from primary to secondary school students, has started. The new school will be ready in early March for the beginning of the new school year.

A plant construction contract was awarded to Heap Leaching Consulting S.A.C. (HLC) in October.

To date,

  • 100 percent of the adsorption / desorption gold processing plant has been fabricated at HLC´s workshop located at Huachipa, on the outskirts of Lima.
  • Items related to the adsorption circuit and cyanide mixing circuit have been transported to La Arena and assembled on site.
  • Diesel operated power supply generators have been delivered to Lima and are awaiting transportation to site.

Reverse circulation (RC) grade control drilling of the first year pit area has commenced and 8,500m of the program have been completed on the Calaorco starter pit area. Approximately 4,000m of RC grade control drilling will commence on the Ethel pit area in mid-January.

The Company's policy is to halt construction activities when operating heavy equipment in wet ground conditions might be less than safe. To date, a total of 15 days of productive construction time has been lost due to rain that caused wet ground conditions.

Currently the project employs 637 people of which 363 people (57 percent) are from local communities located within a 20km radius of the project. A total of 480,000 man hours have been worked to date and the Company is pleased that there have only been two minor lost time incidents. At present, the project has 65 pieces of mobile equipment and portable plant equipment under contract of which a large percentage are provided by local sub-contractors.

Run of mine ore is planned to be loaded onto the pad in January with irrigation commencing in February. Commissioning of the processing plant will commence in March and gold doré production is scheduled for late April. This timing may be affected if heavy rains negatively impact construction activities.

Alex Black, Rio Alto´s President stated, "A tremendous amount of work has been accomplished at La Arena during the past five months which is a credit to the talent, capability and focus of Rio Alto´s management, staff, consultants and contractors who have worked as a close-knit team with the objective of achieving gold production as quickly and safely as possible. Rio Alto and members of the local communities are looking forward to celebrating the mine commissioning and opening of the new school in the new year."

Source: Rio Alto Mining Limited

Tell Us What You Think

Do you have a review, update or anything you would like to add to this news story?

Leave your feedback
Your comment type
Submit

While we only use edited and approved content for Azthena answers, it may on occasions provide incorrect responses. Please confirm any data provided with the related suppliers or authors. We do not provide medical advice, if you search for medical information you must always consult a medical professional before acting on any information provided.

Your questions, but not your email details will be shared with OpenAI and retained for 30 days in accordance with their privacy principles.

Please do not ask questions that use sensitive or confidential information.

Read the full Terms & Conditions.