Robex Increases Production Target By 53% Following $4 Million Funding

Robex Resources Inc. is pleased to inform its shareholders that, following the funding of $4 million announced last week (see News Release 22-04 -2013), its production target set out after commissioning of its plant are increased by 53%.

In recent months, the Robex team and an engineering firm have worked extensively on optimizing the process of the plant. The flow sheet of the process was optimized and redefined. In addition, the equipment has been sized accordingly by the engineering firm. Furthermore, multiple tests have confirmed that a cyanidation time of 16 hours was adequate to maintain the recovery rate at 88% - 90%. As a result, the production target set for the commissioning of its plant in the third quarter of 2013 is now 2,300 tonnes per day (t / d), compared to the objectives of 1500 t / d initially planned. During the year following the start of the plant, the Company expects to achieve 6000 t / d by the gradual addition of cyanidation tanks.

The construction and planned expansions will be realized in three phases: Phase 1, the current phase of start-up includes the feed system, the cyanidation circuit (CIL) and the gold recovery system. Phase 2 includes the crushing and grinding circuit and phase 3 of a second feed circuit. Each phase includes sub-phases. These sub-phases correspond to the gradual addition of cyanide tanks. The exploration of the Mininko property will continue meanwhile with the objective of increasing the resource to such level that it could possibly increase future level of production at Nampala beyond the 6000 tonnes per day planned. In the event of a significant increase in resources, the second and third phases of expansion could proceed eventually.

Reminder on the Nampala mining project

Recall that in October 2012, the Company announced its desire to launch a gold production with a plant having a capacity of about 1500 t / d and increase quickly and sequentially until the threshold of 6,000 t / d (approximately 45.000 ounces of gold per year), as specified in the feasibility study, is reached. (This feasibility study was made public by a press release on November 8, 2011.) The Company also announced expansions at the mill when the construction of the first phase would be completed.

Andre Gagne, President and CEO, said: "This increase in production and therefore, anticipated revenues, will have a significant impact on the Company. Indeed, they will allow Robex to virtually be able to finance the funds generated for future expansions. Thus, the funds generated by the potential exercise of warrants issued in prior funding, and aimed at addressing said expansions, will be mainly engaged in the advancement of other properties to prepare for other development projects."

PROJECT-CONSTRUCTION

To date, construction is well underway. There are nearly a hundred workers on site daily, including a team of 12 Quebec expatriates. The first four cyanidation process tanks and clean water tank have their concrete foundation complete and the assembly of the steel has begun. The "rompad" is at the concreting phase, the buffer pool is finished and work on the tailing dam is advancing very quickly. The housing of the base of life has begun to be occupied by expatriate workers and the refectory is nearing completion. The administrative offices are completed, furnished and operational and the arrival of the satellite internet is due in the coming days. All drilling wells, water supply and dewatering is completed. All access roads to power lines are also completed and ready to receive the posts. Finally, the security perimeter fence of the mine, nearly 10 km, is closed off and the access gate is completed.

You can view pictures of the progress of the work in Nampala on the Robex website.

Source: http://www.robexgold.com/

Citations

Please use one of the following formats to cite this article in your essay, paper or report:

  • APA

    Robex Resources Inc.. (2019, February 17). Robex Increases Production Target By 53% Following $4 Million Funding. AZoMining. Retrieved on April 19, 2024 from https://www.azomining.com/News.aspx?newsID=8126.

  • MLA

    Robex Resources Inc.. "Robex Increases Production Target By 53% Following $4 Million Funding". AZoMining. 19 April 2024. <https://www.azomining.com/News.aspx?newsID=8126>.

  • Chicago

    Robex Resources Inc.. "Robex Increases Production Target By 53% Following $4 Million Funding". AZoMining. https://www.azomining.com/News.aspx?newsID=8126. (accessed April 19, 2024).

  • Harvard

    Robex Resources Inc.. 2019. Robex Increases Production Target By 53% Following $4 Million Funding. AZoMining, viewed 19 April 2024, https://www.azomining.com/News.aspx?newsID=8126.

Tell Us What You Think

Do you have a review, update or anything you would like to add to this news story?

Leave your feedback
Your comment type
Submit

While we only use edited and approved content for Azthena answers, it may on occasions provide incorrect responses. Please confirm any data provided with the related suppliers or authors. We do not provide medical advice, if you search for medical information you must always consult a medical professional before acting on any information provided.

Your questions, but not your email details will be shared with OpenAI and retained for 30 days in accordance with their privacy principles.

Please do not ask questions that use sensitive or confidential information.

Read the full Terms & Conditions.