Energizer Starts Pilot Plant for Madagascar Molo Graphite Project

Energizer Resources Inc. (“Energizer” or the “Company”) is pleased to announce that it has commissioned and started up the pilot plant for its flagship Molo Graphite Project in Madagascar.

Mechanical commissioning of the Molo Graphite Project pilot plant has been completed and two continuous 80-hour campaigns to optimize metallurgical conditions will be completed in the next 30 days. The pilot plant was designed, built, and is being operated by SGS Canada Inc. (“SGS”) in Lakefield, Ontario.

Two hundred tonnes of composite graphite ore was transported last month from the Molo deposit via existing, serviceable infrastructure to SGS in preparation for the pilot plant. Representatives from Caracle Creek International Consulting (“CCIC”) were on site to ensure the ore extracted from the Molo deposit was a true representative sample of the mill feed that will eventually be treated in the future processing plant and that it would satisfy the required standards for use in the upcoming Bankable Feasibility Study (“BFS”). CCIC was the Qualified Person (“QP”) for the recently completed Preliminary Economic Assessment (“PEA”) study and will also be retained as QP for the upcoming BFS.

Multi-Tonne Samples of Graphite Concentrate Ready for Shipment to Potential Partners in November

The Company expects the pilot plant to produce between 7 to 9 tonnes of finished, flaked graphite concentrate within the next 30 days. The pilot plant will enable the Company to optimize flake size, quality and purity to meet the various specifications that have been requested by several potential off take partners. This in turn will allow them to adequately evaluate the finished Molo graphite concentrate and its ability to meet the requirements of their customers – the ultimate end users of the product. The pilot plant will also provide key operational data that will be used to generate process design criteria for the BFS.

Craig Scherba, President & COO stated, “Energizer has reached yet another significant milestone with the commissioning and operation of our pilot plant, which is a critical component of Molo’s mine development plan. We are extremely pleased that by the end of November, tonnes of our finished graphite will be in the hands of several potential off take partners for evaluation.”

The Company looks forward to reporting the final test results from the pilot plant over the next several weeks. As the Company previously reported, the recent metallurgical results from the optimization testing resulted in a significantly improved quality of the flotation concentrate, in terms of both grade and size distribution versus those reported in the Company’s PEA Study.

Potential Ability To Produce High Volume Quantities Of Both Premium Priced Large Flake And Ultra-High Purity Finished Graphite Products

The optimization testing at SGS confirmed that nearly half (47.4%) of the Molo graphite concentrate is classified as the premium-priced large & jumbo flake size (greater than +80 mesh). In conjunction with the test results that confirmed that the Molo graphite concentrate could be easily upgraded to the ultra high purity of greater than 99.9% carbon, the Company will be well positioned to sell finished product to a wide range of end users at premium prices.

DRA Mineral Projects, Africa’s leading mine builder has been retained to complete the Molo BFS and subject to project financing, will be subsequently commissioned for design, construction and operation of the future mine. It should be noted that the BFS will incorporate revised CAPEX and OPEX numbers generated from the latest enhanced and optimized metallurgical results versus the existing data that was used and reported in the Company’s latest PEA study. This is expected to have a positive impact on the already robust Internal Rate of Return (“IRR”) and Net Present Value (“NPV”) of the Project.

Source: http://www.energizerresources.com/

Citations

Please use one of the following formats to cite this article in your essay, paper or report:

  • APA

    NextSource Materials Inc. (2019, February 17). Energizer Starts Pilot Plant for Madagascar Molo Graphite Project. AZoMining. Retrieved on April 20, 2024 from https://www.azomining.com/News.aspx?newsID=8850.

  • MLA

    NextSource Materials Inc. "Energizer Starts Pilot Plant for Madagascar Molo Graphite Project". AZoMining. 20 April 2024. <https://www.azomining.com/News.aspx?newsID=8850>.

  • Chicago

    NextSource Materials Inc. "Energizer Starts Pilot Plant for Madagascar Molo Graphite Project". AZoMining. https://www.azomining.com/News.aspx?newsID=8850. (accessed April 20, 2024).

  • Harvard

    NextSource Materials Inc. 2019. Energizer Starts Pilot Plant for Madagascar Molo Graphite Project. AZoMining, viewed 20 April 2024, https://www.azomining.com/News.aspx?newsID=8850.

Tell Us What You Think

Do you have a review, update or anything you would like to add to this news story?

Leave your feedback
Your comment type
Submit

While we only use edited and approved content for Azthena answers, it may on occasions provide incorrect responses. Please confirm any data provided with the related suppliers or authors. We do not provide medical advice, if you search for medical information you must always consult a medical professional before acting on any information provided.

Your questions, but not your email details will be shared with OpenAI and retained for 30 days in accordance with their privacy principles.

Please do not ask questions that use sensitive or confidential information.

Read the full Terms & Conditions.