Posted in | News | Silver | Mining Business

Prophecy Provides Update on Pulacayo Silver-Zinc-Lead Project

Prophecy Development Corp. ("Prophecy" or the "Company") is pleased to provide the following update on progress at its Pulacayo project:

The Pulacayo silver-zinc-lead project is located in southern Bolivia, close to major silver mining projects operated by Coeur Mining, Inc. (San Bartolome), Pan American Silver Corp. (San Vicente), and Sumitomo Corporation (San Cristobal). Pulacayo is fully permitted for mining and processing up to 560 tonnes of ore per day.

After Mercator Geological Services Limited ("Mercator") produced the technical report compliant with National Instrument 43-101 ("NI 43-101") disclosing the resource estimate for the Pulacayo deposit prepared according to the CIM Definition Standards for Mineral Resources and Reserves (the "CIM Standards") and filed by the Company on July 31, 2015 which outlined 1.27 million tonnes of indicated resource grading 530g/t Ag, 2.51% Pb and 3.63% Zn and a further 350,000 tonnes of inferred resource grading 419g/t Ag, 2.47% Pb and 4.58% Zn* (refer to the Company's news release dated June 18, 2015), the Company has undertaken detailed engineering studies (for production scenarios ranging from 50 to 500 tonnes per day) with the aim to bring Pulacayo into production at the minimum capital expense considering the current challenging metals market.

*inferred resources do not have demonstrated economic viability, are speculative, and are not to be relied on

Milling and Processing

Prophecy's management has evaluated the options of on-site milling (Pulacayo) vs. toll milling at Potosi.

Potosi is located approximately 180km from the Pulacayo project and is connected by a recently paved highway which is in excellent condition. Potosi has a population of approximately 180,000 inhabitants and hosts the existing Cerro Rico deposit, with its centuries of silver-lead-zinc mining production that is still active to this day. There are approximately 100 privately owned, small-sized (i.e. 50 to 500 tonnes per day) facilities capable of toll milling and processing ore that produce zinc and lead concentrates sold to a number of active traders such as Trafigura Beheer BV, Glencore plc and Louis Dreyfus Commodities (Suisse) S.A. A number of those facilities have decreased their processing activities due to a lack of quality feed resulting from a combination of low metal prices and the government's increasing safety restrictions on mining at Cerro Rico.

Prophecy's representatives visited over 30 milling facilities in Potosi and received a number of toll milling and custom milling offers. The Company has calculated the all-in cost to be USD$35 to USD$40 per tonne, which includes transportation of ore from Pulacayo to Potosi, labor, power, water, equipment rental, and re-agents to produce zinc and lead concentrates.

In the past months, the Company has worked with multiple Chinese and local Bolivian suppliers to obtain the best equipment, procurement and construction ("EPC") proposal terms for a mineral processing facility at the Pulacayo project. The EPC proposals include: concrete foundation, equipment housing, purchase and assembly of crusher, mill, flotation cells, water and power connections, and a tailings storage facility. The processing capacity of the tendered facilities range from 200 tonnes per day to 500 tonnes per day with proposed pricing ranges from USD$4-8 million with a 10-month construction period. The approved designated facility site is located 2km from the Pulacayo mine and is permitted to process up to 560 tonnes of feed per day.

Depending on funding availability and market conditions, the Company may pursue toll milling at Potosi or on-site milling at Pulacayo or both in parallel.

Mining

Prophecy's engineering team completed detailed mine plans, which are published on the Company's website, that encapsulate 80% of Pulacayo deposit resources.

Apogee Silver Ltd. ("Apogee"), the former owner of the property, completed over 1,200m of tunneling (2.5m x 2.5m) at level 0 in its 2012-2013 trial mining run that produced 7,547 tonnes of ore grading 339 g/t Ag, 3.8% Pb and 3.1% Zn (refer to the Company's news release dated December 5, 2014). Upon close mine inspection, Prophecy's engineering team determined: (1) there are resources left over from Apogee's mined areas; and (2) minimal additional tunnel development is required to access the nine planned stopes.

The Company is planning and designing stopes at level 0 and level +40 based on existing drill hole data, sampling data and historic mining records with the goal of sustained mining at the rate of 300 tonnes per day for the first 12 months and will postpone central shaft rehabilitation to access resources below level 0. In addition to the Company's Pulacayo deposit, its Pacamayo and Paca deposits can be turned into sources for mill feed upon completion of certain geological, engineering, and feasibility work. The Pacamayo deposit is being actively mined on a small scale by local workers and recent samples taken by Prophecy returning silver grades between 2,548 g/t and 7,380 g/t (refer to the Company's news release dated September 18, 2015). The inferred resource estimate* prepared according to the CIM Standards and disclosed according to NI 43-101 for the Paca deposit is estimated at 1.26 million tonnes at 363 g/t Ag, 1% Zn and 1% Pb, with 95% of the resource being within 100m from the surface. Recent surface samples taken 1km north of the Paca deposit returned 833 g/t Ag (refer to the Company's news release dated August 27, 2015).

*inferred resources do not have demonstrated economic viability, are speculative, and are not to be relied on

The Company performed an equipment audit and analysis at Pulacayo and concluded that there is sufficient equipment to start mining at the rate of 50 tonnes per day, without any additional capital expenditure. Existing equipment includes 25 2-tonne wagons, three battery powered locomotives, 10 stopers, a fan, and a compressor -- all of which, are operational and in good condition. Ample power and water are available on site to support continued mining operation at the minimum of 50 tonnes per day. A shrinkage stoping method will be utilized with two to three men per shift, three shifts per day for each stope.

It will require approximately 90 days for the Company to start mining at Pulacayo, which includes notification to, and receipt of approval from, relevant agencies for Prophecy's mine plan, procurement of fuel, lubricants and explosives, and sourcing experienced labor from the Pulacayo cooperatives who are residents of the town of Pulacayo, located 1km from the mine.

To achieve production rates of 300-500 tonnes per day would require modest power transformer upgrade and extra sets of mining equipment totaling approximately USD$2-3 million (300tpd vs. 500 tpd) in order to commission multiple stope development in parallel.

The Company continues to study optimal mining production and processing scenarios and will announce a production decision at the conclusion of the study.

Bolivia

Bolivian President, Evo Morales recently visited New York and several European cities accompanied by a large number of Bolivian officials and businessmen to promote Bolivia as an attractive foreign investment destination. Credit rating agencies recently upgraded Bolivia's debt rating, highlighting its prudent fiscal discipline, stable currency in a growing economy, strengthened legal framework to protect private investment and reduced nationalization risk. The Company believes the Pulacayo project is an attractive silver mining project backed by a local community with a strong mining tradition in an increasingly foreign investment-friendly jurisdiction.

Qualified Persons

The technical content of this news release was reviewed and approved by Christopher M. Kravits, P. Geo., who is a Qualified Person within the meaning of NI 43-101. Mr. Kravits is a consultant to the Company and serves as its Qualified Person and General Mining Manager.

Source: http://www.prophecydev.com/

Tell Us What You Think

Do you have a review, update or anything you would like to add to this news story?

Leave your feedback
Your comment type
Submit

While we only use edited and approved content for Azthena answers, it may on occasions provide incorrect responses. Please confirm any data provided with the related suppliers or authors. We do not provide medical advice, if you search for medical information you must always consult a medical professional before acting on any information provided.

Your questions, but not your email details will be shared with OpenAI and retained for 30 days in accordance with their privacy principles.

Please do not ask questions that use sensitive or confidential information.

Read the full Terms & Conditions.