Posted in | News | Silver | Mining Business

Aurcana Reports 5% Increase in Silver Production in Q3 2013

Aurcana Corporation ("Aurcana" or the "Company") wishes to report its unaudited financial results for the third quarter ended September 30, 2013.

The Q3 2013 Earnings Webcast and Conference Call has been scheduled for 11:00am Pacific Time (2:00 pm Eastern Time) on Monday December 2, 2013. See the bottom of this press release for details.

Highlights of Third Quarter ended September 30, 2013:

  • Total silver equivalent ounces produced in Q3 2013 increased by 5% to 754,788 oz, compared to 718,063 oz in Q3 2012.
  • Total silver equivalent produced for the first 9 months of 2013 increased by 14% to 2,165,865 oz, compared to 1,899,281 oz during the same period one year ago.
  • Total Cash Cost, net of by-product credits, was $6.45 per ounce, down 17% from $7.79 in Q2 2013 and up 9% from $5.90 in Q3 2012.
  • The cash cost per milled tonne for Q3 2013 was $32.85 vs. $32.50 in Q3 2012;
  • Total Revenues for Q3 2013 were $10.4 million, down $4.6 million from $15.0 million in Q3 2012, due to a combination of lower silver prices, lower grade material mined in the development of new producing areas and higher unsold inventories at the end of the period;
  • Total Earnings from mining operations for Q3 2013 were $2.6 million and $9.9 million for the first 9 months of 2013;
  • Net loss for Q3 2013 was $15.5 million. Included in the third quarter net loss of $15.5 million, the Company recorded an impairment charge related to Shafter property, plant, equipment and mineral properties of $6,138,442 and also recorded a total of $6,813,729 for certain expenses incurred at Shafter mine during the first nine months of 2013.

The summary of the selected financial information should be read in conjunction with the unaudited financial statements and the related management's discussion and analysis for the three and nine month periods ended September 30, 2013, together referred to as the "Financial Statements" filed on www.sedar.com and available on www.aurcana.com. All figures are in US dollars unless otherwise noted.

Third Quarter Production and Operational Highlights

La Negra Mine

  • During Q3 2013 La Negra's mill averaged 2,632 tonnes per day ("tpd"), a 15% increase from 2,289 tpd averaged during Q3 2012.
  • The average silver grade during Q3 2013 was 55 grams per tonne ("g/t"), compared to 80 g/t in 2012. The decrease in silver grade during this period was due to an increase in mine development to support higher mine production rates in the future. Currently sufficient mine development has been completed at the La Negra mine to support two years of production and Aurcana will therefore reduce mine development at La Negra in the short term. La Negra's mine plan includes a transition to mining higher silver grade mineralized zones from the upper levels of the La Negra mine in 2014 and 2015.
  • Aurcana has ordered a raise-boring machine to construct ventilation raises and ore passes to provide ventilation in the new mining areas and allow for the transfer of ore via gravity from the upper levels to the main haulage level below. It is anticipated that this will increase productivity and reduce operating costs. The raise-borer is expected to be commissioned in Q2 2014.
  • The inventory of copper/silver concentrates increased to 1,705 tonnes, with commensurate reductions in metal sales and revenues. The mine and plant expansion combined with greater production from the copper-rich lower levels of La Negra resulted in higher copper concentrate production than anticipated exceeding the capacity of the existing filter press and constraining mill throughput. A new larger capacity filter press has been received and is expected to be commissioned in Q1 2014. This improvement is expected to allow for sustainable production at the targeted 3,000 tpd level.
  • During Q2 2013, the Company initiated a planned 15-hole, 5,000 metre surface drill program in order to better define gold mineralization announced on February 11, 2013. A total of 1,773 meters were drilled but gold values lacked continuity and the program was terminated.
  • Underground diamond drilling and mine development at La Negra continue to delineate additional mineralized zones. Drill crews completed 10,128 metres of diamond drilling during 2013 versus 9,399 meters for the same period one year ago. La Negra scheduled 13,500 meters of drilling for completion in 2013 versus 13,311 meters drilled in 2012. Drilling objectives are to better define mineralized zones to support short and medium term mine planning.
  • In response to lower silver prices, La Negra has undertaken cost cutting measures to improve margins while also cutting back on capital expenditures. These include:
    • Suspension of surface exploration diamond drilling activities;
    • Refocusing mine development to areas of higher grade mineralization;
    • Reducing the use of contractors;
    • Optimizing power usage by rescheduling certain activities, particularly crushing, to off-peak hours thereby reducing energy costs; and
    • Improving equipment maintenance to increase utilization rates and productivities thereby reducing the need for additional capital investment.

Shafter Mine

  • The Company continues to make capital improvements to the processing facility at Shafter to improve throughput rates and recoveries.
  • The Shafter plant while still in commissioning and development processed a total of 46,516 tons during Q3 2013, an average of 505 tpd. Throughput was limited due to shortages of spare parts and mining resources brought upon by lack of funding prior to the Company's debt financing which closed in September, 2013. Mechanical problems with the ball mill curtailed commissioning in October. The necessary parts for repair are on order and the mill should be repaired by January 2014.
  • The current April 2001 block model of the Shafter mineralized resources, used to support the June 2011 feasibility study, has been an inconsistent predictor of tons and grade in the old Presidio Mine area and new remodeling is being undertaken by Mine Development Associates ("MDA") of Reno Nevada. This work, when complete, together with a re-evaluation of project economics with respect to lower silver prices, will determine new higher cut-off grades and optimum throughput rates for both mine and mill.
  • Concurrently, plans are being developed to rehabilitate the mine shafts, hoisting systems and mine dewatering system in the eastern extension of the ore body thereby allowing access to this non-mined area delineated by Gold Fields in the late 70's and early 80's. This work will be followed up with a comprehensive mine plan with subsequent development of production stopes to complement production from the old Presidio Mine area.
  • An equipment malfunction (turbo failure) on November 1, 2013 resulted in smoke generation and a suspicion of fire underground, which later proved to be incorrect. The subsequent precautionary mine evacuation and MSHA investigation has caused all mining operations to be suspended while the mine ventilation system is being upgraded.
  • The curtailment of underground operations, probably through mid-December 2013, will delay planned underground diamond drilling and mine development.
  • In the first nine months of 2013, capitalized expenses (net of proceeds generated from silver sales) totaled $9.6 million.
  • The total capital costs required for the process facility to design capacity were originally estimated to be approximately $18.5 million, of which some $5.5 million has been spent as of the end of Q2 2013. Capital outlays have been reassessed and some $5 million of the original amount have now been deferred indefinitely while preserving the ability to reach a sustainable throughput and acceptable recoveries. However, the funds previously allocated to these deferred costs will now be required to rehabilitate the infrastructure to allow for the exploitation of the eastern non-mined extension of the Shafter mineralized zone.
  • In August 2013 a second new tailings filter press was received and commissioned. This replaced the second of three used low-capacity tailings filter presses that were contributing to operational delays and reduced recovery rates. The upgrade in filter presses is a continuation of several plant improvements designed to reach the planned throughput.
  • New precipitate filter presses were received and commissioned in October 2013. Additional refinery equipment is arriving and will be installed and commissioned in Q4 of 2013.
  • Foundation work has commenced on the three counter current decantation (CCD) and new primary thickener tanks in October 2013. Actual tank fabrication is commencing January 2014 with a goal to have a fully operational circuit during Q2 2014.
  • Proposals are being solicited for targeted automation of process plant components to achieve improved process control and lower reagent consumptions. Planning has commenced to replace liquid cyanide shipments with solid briquettes to reduce transportation costs. Some of the components necessary for this improvement are already in place and minimum capital expense will be required for the transition.

Conference call details

Conference date: Monday, December 2, 2013
Conference time: 11:00AM Pacific Time / 2:00pm EST
Participant dial-in number(s): Can: 416-340-2216 / US & Canada: 866-223-7781 / Int: 800-6578-9898
Participant pass code: Not required

The recorded conference call will be posted to Aurcana's website.

Please follow this link for the upcoming Aurcana webcast: http://www.gowebcasting.com/5112

Financial Statements and MD&A

To read complete Financial Statement and MD&A please visit: www.aurcana.com, or www.sedar.com.

Source: http://www.aurcana.com/

Citations

Please use one of the following formats to cite this article in your essay, paper or report:

  • APA

    Aurcana Silver Corporation. (2019, February 17). Aurcana Reports 5% Increase in Silver Production in Q3 2013. AZoMining. Retrieved on April 23, 2024 from https://www.azomining.com/News.aspx?newsID=9043.

  • MLA

    Aurcana Silver Corporation. "Aurcana Reports 5% Increase in Silver Production in Q3 2013". AZoMining. 23 April 2024. <https://www.azomining.com/News.aspx?newsID=9043>.

  • Chicago

    Aurcana Silver Corporation. "Aurcana Reports 5% Increase in Silver Production in Q3 2013". AZoMining. https://www.azomining.com/News.aspx?newsID=9043. (accessed April 23, 2024).

  • Harvard

    Aurcana Silver Corporation. 2019. Aurcana Reports 5% Increase in Silver Production in Q3 2013. AZoMining, viewed 23 April 2024, https://www.azomining.com/News.aspx?newsID=9043.

Tell Us What You Think

Do you have a review, update or anything you would like to add to this news story?

Leave your feedback
Your comment type
Submit

While we only use edited and approved content for Azthena answers, it may on occasions provide incorrect responses. Please confirm any data provided with the related suppliers or authors. We do not provide medical advice, if you search for medical information you must always consult a medical professional before acting on any information provided.

Your questions, but not your email details will be shared with OpenAI and retained for 30 days in accordance with their privacy principles.

Please do not ask questions that use sensitive or confidential information.

Read the full Terms & Conditions.