Rio Tinto Invests $55 Million to Begin Underground Mining at Kennecott Copper Operations

Rio Tinto has approved a $55 million[1] investment in development capital to start underground mining and expand production at its Kennecott copper operations in Utah, United States.

Underground mining will initially focus on an area known as the Lower Commercial Skarn (LCS), which will deliver a total of around 30kt[2] of additional high quality mined copper through the period to 2027 alongside open cut operations. The first ore is expected to be produced in early 2023, with full production in the second half of the year. It will be processed through the existing facilities at Kennecott, one of only two operating copper smelters in the United States.

Kennecott holds the potential for significant and attractive underground development. The LCS is the first step towards this, with a Mineral Resource of 7.5 Mt at 1.9% copper, 0.84 g/t gold, 11.26 g/t silver, and 0.015% molybdenum identified based on drilling and a Probable Ore Reserve of 1.7 Mt at 1.9% copper, 0.71 g/t gold, 10.07 g/t silver, and 0.044% molybdenum[3].

Underground battery electric vehicles are currently being trialled at Kennecott to improve employee health and safety, increase productivity and reduce carbon emissions from future underground mining fleets. A battery electric haul truck and loader supplied by Sandvik Mining and Rock Solutions are being used to evaluate performance and suitability as part of underground development work.

Rio Tinto Copper chief executive Bold Baatar said, "This investment will allow us to quickly bring additional volumes of high quality copper to the market and build our knowledge and capabilities as we evaluate larger scale underground mining at Kennecott. We are progressing a range of options for a significant resource that is yet to be developed at Kennecott, which could extend our supply of copper and other critical materials needed for electric vehicles and renewable power technologies.

"Trialling underground battery electric vehicles is an exciting step in our work to create a safer workplace for our employees, increase the productivity of the mine and reduce emissions from our operations. We look forward to seeing their potential for deployment."

Existing undergound infrastructure is currently being extended to enable early access to the next underground resource and undertake characterisation studies. A Feasibility Study to inform decisions on the next phase of underground production is expected to be completed in 2023. This will be one of several potential stages currently being investigated.

Feasibility studies are also being progressed to extend open pit mining at Kennecott beyond 2032.

The Table 1 Release was made in accordance with the JORC Code and the ASX Listing Rules. Mineral Resources are reported in addition to Ore Reserves. Mineral Resources and Ore Reserves are quoted on a 100 per cent basis.

A copy of the Table 1 Release is available on Rio Tinto's website at: riotinto.com/invest/financial-news-performance/resources-and-reserves

(1) All dollar values are in USD.

(2) Lower Commercial Skarn production targets referred to in this release are reported as recoverable copper and are underpinned as to 100% by Probable Ore Reserves. These estimates of Ore Reserves were reported in a release to the Australian Securities Exchange (ASX) dated 31 August 2022 "Rio Tinto Kennecott Mineral Resources and Ore Reserves" (Table 1 Release) and have been prepared by Competent Persons in accordance with the requirements of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves, 2012 (JORC Code).

(3) The Mineral Resource and Ore Reserve estimates referred to in this release were set out in the Table 1 Release. The Competent Person responsible for the information in that release that relates to Mineral Resources is Mr Ryan Hayes, a Member of the Australasian Institute of Mining and Metallurgy (MAusIMM). The Competent Person responsible for the information in that release that relates to Ore Reserves is Mr Stephen McInerney, a Member of the Australasian Institute of Mining and Metallurgy (MAusIMM). Rio Tinto confirms that it is not aware of any new information or data that materially affects the information included in the Table 1 Release, that all material assumptions and technical parameters underpinning the estimates in the Table 1 Release continue to apply and have not materially changed, and that the form and context in which the Competent Persons' findings are presented have not been materially modified.

This announcement is authorised for release to the market by Steve Allen, Rio Tinto's Group Company Secretary.

Source: https://www.riotinto.com/

Tell Us What You Think

Do you have a review, update or anything you would like to add to this news story?

Leave your feedback
Your comment type
Submit

While we only use edited and approved content for Azthena answers, it may on occasions provide incorrect responses. Please confirm any data provided with the related suppliers or authors. We do not provide medical advice, if you search for medical information you must always consult a medical professional before acting on any information provided.

Your questions, but not your email details will be shared with OpenAI and retained for 30 days in accordance with their privacy principles.

Please do not ask questions that use sensitive or confidential information.

Read the full Terms & Conditions.